| Project
Name |
GVTA Bus Wash Replacement |
Client
|
Greater Vancouver Transportation Authority
Trans Link
Roger Schmidt
Ph: 604-453-4597 |
| Location |
Burnaby - 3750 Kitchener Street
Coquitlam - 2061 Kingsway Avenue |
| Size (sq.ft) |
|
| Value |
$ 754,975 |
| Project Description |
This project was to replace existing bus wash equipment at
two separate locations. A custom designed wash was built by Sherman Supersonic
Industries of Mississauga to meet the specific needs of the Coast Mountain
Bus Company. These washes were shipped out and installed by local forces.
Significant mechanical, electrical, and civil upgrades were required to
interface with the new washes.
This project was started in August 2004 and completed in February 2005. |
| Team Members |
Project Manager – Jarett Hayes
Superintendent – Brad Taylor |
| Architects & Engineers |
Engineer
Mateo Ecejo of Earth Tech Canada Inc.
Ph: 604-298-6181
|